Since the provincial Conservative government announced its intention to extend SkyTrain from Surrey City Centre to Newton, a familiar narrative has emerged. Pundits and skeptics are already claiming Surrey residents shouldn’t expect to ride a train to Newton for ten years, fifteen years, or perhaps ever. Others are using this uncertainty to revive calls for Bus Rapid Transit (BRT) or at-grade Light Rail Transit (LRT).
At SkyTrain for Surrey, we believe it is important to separate facts from speculation—and what we can do is look at history.
When rapid transit projects have become government priorities in British Columbia, they have often advanced far more quickly than many people remember. Metro Vancouver’s own SkyTrain network contains several examples where major extensions moved from political commitment to passenger service in substantially less than a decade.
Here is what history actually tells us about how fast SkyTrain can be built.
The clearest blueprint for a Newton extension is the SkyTrain project currently under construction down Fraser Highway.
Before the COVID-19 pandemic disrupted global supply chains, the Surrey Langley SkyTrain (SLS) was on track to open by late 2025—just seven years after initial approval.
While pandemic-era inflation and labour shortages eventually pushed completion to 2028 (and now 2029), the original pre-pandemic schedule remains a textbook example of how rapidly a SkyTrain project can advance when funding, governance, and political will align.
In December 2018—immediately after Surrey cancelled the Surrey-Newton-Guildford LRT—TransLink staff presented a clear work plan to the Mayors’ Council: 15 months for project development and a business case + 15 months for procurement + 4 years for construction.[1]
TransLink noted that planners could accelerate work by drawing on past internal corridor assessment work (“from 2015 to 2017”) and lessons learned from the recently completed Evergreen SkyTrain Extension. That exact same head start exists today for the Newton corridor.
Under TransLink’s leadership, the SLS project stayed right on schedule:
In March 2020—just weeks before an expected funding announcement—COVID-19 hit. By May, TransLink had shelved its region-wide “Phase 2” transit plan, leaving the SLS in limbo.
Ultimately, a fall 2020 provincial election commitment to build all 16 kilometres at once, followed by federal funding in July 2021, got the project moving again. However, a 2022 updated business case extended the construction and commissioning timeline from 15 quarters to 20 (Q4 2023 to Q3 2028) to account for post-pandemic labour and material constraints.[4]
Despite those extraordinary disruptions, the pre-2020 record suggests that under normal conditions, TransLink can take a Surrey SkyTrain extension from concept to opening day in roughly five to seven years.
The project that ultimately became the Millennium Line emerged from planning work that began in early 1998. Then known as the “Broadway-Lougheed Rapid Transit corridor”, decision-makers at the time were examining at-grade light rail transit (LRT) options that differed substantially from the final Millennium Line SkyTrain project.
However, in June 1998, the province pivoted to SkyTrain technology as part of a deal bringing a new Bombardier manufacturing plant to B.C.[5] Because of the switch in technologies from LRT to SkyTrain (necessitating changes such as planning for full grade separation), work on the project essentially had to start from scratch.
Archival records we reviewed at the Vancouver Central Library show an astonishing pace of development:
Meaning that, in less than 12 months, the Millennium Line went from zero dedicated SkyTrain engineering to virtually shovel-ready.
Construction began in New Westminster in October 1999[7]. Less than three years later, the initial 3.5-kilometre segment from Columbia to Braid opened in January 2002, followed by the full 19-kilometre line to Commercial Drive in August 2002.
While the political, economic, and regulatory environment of the late 1990s differed from today, the Millennium Line remains an important reminder that major transit projects do not necessarily require a decade or more between announcement and opening. When governments treat rapid transit as a priority, planning, approvals, procurement, and construction can overlap and proceed on accelerated schedules.

Perhaps the most impressive precedent is the Canada Line—Metro Vancouver’s first majority-tunnelled rapid transit line, built with its own dedicated operations and maintenance centre. It introduced a new train technology, required the construction of extensive bored and cut-and-cover tunnels, crossed multiple municipalities, and was tied to the immovable deadline of the 2010 Winter Olympics.
Despite massive engineering complexity and fierce political hurdles, it went from initial procurement in April 2003 to opening day in August 2009—a period of just over 6 years.[8]
Originally announced alongside the Millennium Line in June 1998 as the Richmond-Airport-Vancouver (“RAV”) line, the project was tied to Vancouver’s bid at the time for the 2010 Winter Olympics, with a bus rapid transit line (the 98 B-Line) serving as an interim measure.[9]
Before breaking ground, the project survived a gauntlet of setbacks that threatened to derail it completely:
In the end, the RAV line project was rescued at the eleventh hour through additional contributions from the province ($65M), TransLink ($101M), and the SNC-Lavalin consortium ($206M). Much of the political heavy lifting to secure that deal was led by TransLink’s Board Chair at the time—former (and current) Surrey Mayor Doug McCallum, who had supported RAV line at all of its May-June 2004 votes.[17][18]
With financing and development finalized in early 2005, contractors raced against a hard deadline: the 2010 Winter Olympics, which had been awarded to Vancouver in 2003 . The earlier setbacks meant that the project now had to proceed on a significantly accelerated timeline.
Just four-and-a-half years later, the 19-kilometre mix of tunnels, elevated guideways, and surface track opened to the public on August 17, 2009—three-and-a-half months ahead of schedule.

Critics who claim a SkyTrain to Newton will take 10 or 15 years are treating worst-case or political delays as an engineering rule.
Taken together, the Millennium Line, Canada Line, and pre-pandemic Surrey Langley SkyTrain timelines point to a consistent takeaway: a five-to-seven-year delivery window is entirely achievable under focused governance.
Furthermore, with existing corridor studies in hand and no major tunnelling required, expanding SkyTrain to Newton is one of the most straightforward rapid transit projects in the region. We recently predicted in a detailed analysis that a 2032-2035 opening year timeline for a Newton SkyTrain extension is achievable.[19]
| Project | Development Start | Opening | Time |
|---|---|---|---|
| Millennium Line | 1998 | 2002 | ~4 years |
| Canada Line | 2003 | 2009 | ~6 years |
| Surrey Langley SkyTrain (original plan) | 2018 | 2025 | ~7 years |
| SkyTrain to Newton (our prediction) | 2027 | 2032-2035 | ~5-8 years |
For the tens of thousands of students, workers, and families who rely on overcrowded buses along King George Boulevard every day, rapid transit isn’t an abstract policy debate—it’s hours of their week on the line. However, history shows that we know how to build SkyTrain quickly when the commitment is real.
As such, the timeline for the Newton SkyTrain extension will ultimately come down to whether our provincial and regional leaders choose to treat Surrey’s transit needs with the same urgency that they brought to SkyTrain lines in the past.
Pictured in header: Surrey Langley SkyTrain construction and gantry at Fleetwood Station (156 Street)
Reality Check
Reality Check is the online blog run by the founder of SkyTrain for Surrey, a BC-based community organization that has advocated for expanding the Vancouver SkyTrain system, including our successful advocacy for the under-construction Surrey-Langley SkyTrain extension and the proposed SkyTrain expansion to Newton.