SkyTrain for Surrey

SkyTrain advocates applaud Surrey City Council’s unanimous support for SkyTrain to Newton, address misinformation on SkyTrain construction timeline and BRT

Last week, Surrey City Council passed a motion instructing City staff to begin work on advancing and supporting a Newton SkyTrain extension. SkyTrain advocates with SkyTrain for Surrey applaud this motion as an important show of unity, as it is clear that more SkyTrain expansion is needed in the city beyond the currently under-construction Surrey Langley SkyTrain (Dave Barrett Extension).

Vancouver, Burnaby, Richmond and New Westminster have 4.4 kilometres of SkyTrain per 100,000 residents[1][2]. Surrey, White Rock, Langley City and Langley Township will still have only 2.7 kilometres of SkyTrain per 100,000 residents even with the completion of both the Surrey Langley SkyTrain and the City Centre-Newton line.[3][4]

A SkyTrain extension instead of the previously proposed King George Boulevard BRT project means that transit riders will experience more reliable commutes and faster travel times, with elevated trains unimpeded by traffic. This will attract thousands of new public transit riders and take huge volumes of cars off the road.

SkyTrain to Newton FAST FACTS
  • Downtown Surrey to Newton Town Centre in just 10 minutes or less.
  • 5 new stations, potentially connected to the existing SkyTrain system.
  • Total travel time of just 50-55 minutes to Waterfront Station in Downtown Vancouver.
  • Over 150,000 people in Newton[5] and a further 90,000 people in South Surrey[6] could benefit from the extension
  • High service frequency, including during off-peak hours, thanks to driver-less operation
  • Trains run 96% on time, all the time.

Misinformation about SkyTrain to Newton construction timeline and BRT

SkyTrain for Surrey is also taking this opportunity to address significant misinformation about the SkyTrain project, amid discussions that it could cause cancellation of the remainder of the King George Boulevard BRT project between Newton and South Surrey:

      1. There has been some concern and discussion amongst other transit advocacy groups in the region that a SkyTrain extension to Newton would only be completed by the year 2037, or possibly even later in the 2040s. SkyTrain for Surrey estimates that an opening date between 2032 and 2035 is reasonable, due to the significantly smaller project (6.5 kilometres, versus 16 kilometres for the Surrey Langley SkyTrain) and the possibility of leveraging Surrey Langley SkyTrain construction infrastructure to help jump-start the expansion to Newton.
      2. In addition, our organization estimates that the BRT segment between Newton and South Surrey would cost only 1/3 as much as the full BRT, due to significantly reduced infrastructure requirements including fewer BRT stations, fewer lane-kilometres of dedicated lanes, and lower traffic mitigation costs as King George Boulevard sees lower traffic volumes south of Newton Town Centre. We thus urge TransLink and decision-makers to retain the BRT project between Newton Town Centre and South Surrey.
      3. Even if the BRT project is ultimately not retained by TransLink, SkyTrain to Newton combined with express bus improvements would result in comparable transit travel times—potentially within 5 minutes or less of the estimated 40-minute BRT travel time to South Surrey.
Concept render of future SkyTrain station at King George Boulevard and 88 Ave in Surrey. Prepared by the SkyTrain for Surrey team.
Concept render of future SkyTrain station at King George Boulevard and 88 Ave in Surrey (by SkyTrain for Surrey)

Alternative 1: Expo Line branch

King George Boulevard SkyTrain concept ALTERNATIVE 1

Alternative 2: Standalone SkyTrain line

King George Boulevard SkyTrain concept - Alternative 2: Standalone SkyTrain line map

Footnotes

  1. 67.6 kilometres total consisting of: the original Expo Line spanning 22.8 km; the Millennium Line Phase I (including the current Columbia to Production-Way University branch operating as the Expo Line) spanning 19.9 km; the Canada Line spanning 19.2 km; and the Broadway Subway spanning 5.7 km[↩]
  2. Population based on 1.53 million people as reported in Metro Vancouver Growth Projections – 2025​ Update​, for the year 2031 in the BURRARD PENINSULA sub-region + Richmond[↩]
  3. 27.9 kilometres total consisting of: the Expo Line from the New Westminster/Surrey border on the SkyBridge to King George Station spanning 5.9 km; the Surrey Langley SkyTrain spanning 16 km; and the future SkyTrain to Newton spanning 6 km[↩]
  4. Population based on 1.02 million people as reported in Metro Vancouver Growth Projections – 2025​ Update​, for the year 2031 in the SOUTH OF FRASER – EAST Sub-Region[↩]
  5. per 2021 Census, as noted by City of Surrey[↩]
  6. per 2021 Census, as noted by City of Surrey[↩]

Concept render of future SkyTrain station at King George Boulevard and 88 Ave in Surrey (by SkyTrain for Surrey)

King George Boulevard SkyTrain - Advocacy Timeline

2012
Surrey Rapid Transit Study

SkyTrain to Newton considered in Surrey Rapid Transit Study Alternatives Analysis (options RRT2, RRT3)

2019 July
TransLink explores SkyTrain to Newton

A cost estimate for SkyTrain on King George Boulevard to Newton was prepared as part of a rework in rapid transit planning with the cancellation of the SNG LRT.

New SkyTrain on King George Boulevard to Newton could cost up to $1.4 billion — Daily Hive Vancouver

2022 April
SkyTrain to Newton considered in Transport 2050

"Proposed investments detailed in the 10-Year Priorities include: ... Exploring other potential SkyTrain extensions, including Newton in Surrey and Port Coquitlam"

TransLink unveils first 10 years of Transport 2050 priorities — TransLink

2022 October
Surrey Municipal Election
Mayoral candidates make promises for SkyTrain

In this election, several Mayoral candidates expressed interest in a King George Boulevard SkyTrain extension to Newton and South Surrey.

2024 October
BC Provincial Election
BC Conservatives make election promise for SkyTrain

The BC Conservatives under John Rustad expressed interest in a King George Boulevard SkyTrain extension to Newton, making it a primary party priority for Surrey.

2026 October 17
Surrey Municipal Election
Mayoral candidates and parties make promises for SkyTrain

In this election, several Mayoral candidates made commitments to develop a King George Boulevard SkyTrain extension to Newton, with some committing to develop a further extension to South Surrey.

2026 October 24
BC Provincial Election
BC NDP and Conservatives promise extending SkyTrain to Newton

After Surrey's election of a new Mayor/Council that has a commitment to championing a SkyTrain extension to Newton, both the BC NDP under David Eby and the BC Conservatives under Lorne Doerkson made commitments to extending SkyTrain to Newton on October 20.

2026 November 9
Surrey City Council unanimously backs Newton SkyTrain

All newly-elected members of Surrey City Council voted unanimously to support the SkyTrain expansion to Newton, including directing City staff to immediately begin work on supporting the project.

SkyTrain for Surrey is a BC-based community organization that has advocated for expanding the Vancouver SkyTrain system, including our successful advocacy for the under-construction Surrey-Langley SkyTrain extension and the proposed SkyTrain expansion to Newton.

Media Contact: Daryl Dela Cruz ​– Founder, SkyTrain for Surrey ・ Phone: +1 604 329 3529, [email protected]

SkyTrain advocates applaud Surrey City Council’s unanimous support for SkyTrain to Newton, address misinformation on SkyTrain construction timeline and BRT